Roadmap
-
7 months late (12/14/07)
17%
- Closed tickets:
- 2
- Active tickets:
- 10
Initial public release of the OpenMRS Lite package
-
6 months late (12/30/07)
71%
- Closed tickets:
- 10
- Active tickets:
- 4
Implement a simple monthly PEPFAR report in the core framework
-
3 months late (03/20/08)
29%
- Closed tickets:
- 2
- Active tickets:
- 5
-
3 months late (04/10/08)
67%
- Closed tickets:
- 10
- Active tickets:
- 5
-
3 months late (04/14/08)
24%
- Closed tickets:
- 5
- Active tickets:
- 16
Bi-directional synchronization with support for all existing domain objects.
-
1 month late (05/31/08)
0%
- Closed tickets:
- 0
- Active tickets:
- 6
-
No date set
0%
- Closed tickets:
- 0
- Active tickets:
- 1
AMPATH Medical Record System version 1.2
-
No date set
44%
- Closed tickets:
- 11
- Active tickets:
- 14
-
No date set
25%
- Closed tickets:
- 1
- Active tickets:
- 3
-
No date set
43%
- Closed tickets:
- 3
- Active tickets:
- 4
-
No date set
0%
- Closed tickets:
- 0
- Active tickets:
- 6
Full Featured Multiplatform, multibundled Installer
-
No date set
33%
- Closed tickets:
- 1
- Active tickets:
- 2
Improve usability of the module.
-
No date set
0%
- Closed tickets:
- 0
- Active tickets:
- 1
All tickets not in the next milestone.
-
No date set
100%
- Closed tickets:
- 27
- Active tickets:
- 0
Enhancements and bug fixes included in the 1.2.02 release
-
No date set
54%
- Closed tickets:
- 87
- Active tickets:
- 74
Assignments due by the 1.3 release
-
No date set
7%
- Closed tickets:
- 2
- Active tickets:
- 25
Assignments due by the 1.4 release
-
No date set
8%
- Closed tickets:
- 4
- Active tickets:
- 44
Features needed/desired eventually, but not necessarily in the near future.
-
No date set
60%
- Closed tickets:
- 6
- Active tickets:
- 4
Partners In Health initial implementation of OpenMRS in Rwanda
-
No date set
0%
- Closed tickets:
- 0
- Active tickets:
- 1
Features needed for PIH's implementation in Rwanda, but not needed for initial implementation